Timeline: Constitution Pipeline

The proposed Constitution Pipeline would carry gas from the Marcellus gas fields of Pennsylvania to the intersection of the Tennessee #200 and the Iroquois pipelines in the Town of Wright, Schoharie County, NY.

2012XJanuaryBegin Development
XFebruaryAnnounce project
XFebruaryOpen season, solicit customers
XMarchContact state government officials
XAprilPre-file with FERC
XAprilCapacity of pipeline fully subscribed
XAprilBegin obtaining survey permissions
XApril/MayContact local government officials
XMayNotify all property owners affected
XJuneBegin ground surveys
XJuneFirst issue of newsletter Update
JulyOpen houses (5), informational
AugustFERC Scoping meetings
FallBegin negotiating easement agreements
OctoberDraft environmental report
2013JanuaryFile 7(c) application with FERC
JanuarySecond issue of newsletter Update
JuneDraft Environmental Impact Statement
SeptemberFinal Environmental Impact Statement
NovemberFERC order of certification
2014JanuaryBegin clearing ROW
AprilBegin construction
2015MarchBegin shipping natural gas