The proposed Constitution Pipeline would carry gas from the Marcellus gas fields of Pennsylvania to the intersection of the Tennessee #200 and the Iroquois pipelines in the Town of Wright, Schoharie County, NY.
2012 | X | January | Begin Development |
X | February | Announce project | |
X | February | Open season, solicit customers | |
X | March | Contact state government officials | |
X | April | Pre-file with FERC | |
X | April | Capacity of pipeline fully subscribed | |
X | April | Begin obtaining survey permissions | |
X | April/May | Contact local government officials | |
X | May | Notify all property owners affected | |
X | June | Begin ground surveys | |
X | June | First issue of newsletter Update | |
July | Open houses (5), informational | ||
August | FERC Scoping meetings | ||
Fall | Begin negotiating easement agreements | ||
October | Draft environmental report | ||
2013 | January | File 7(c) application with FERC | |
January | Second issue of newsletter Update | ||
June | Draft Environmental Impact Statement | ||
September | Final Environmental Impact Statement | ||
November | FERC order of certification | ||
2014 | January | Begin clearing ROW | |
April | Begin construction | ||
2015 | March | Begin shipping natural gas |